News Flash

Latest News

Posted on: October 4, 2019

Park Road Trail Work Continues, Saturday Work Hours Approved

Update October 11, 2019

Saturday work hours have been approved by the Township for the completion of the Park Road Trail project. On Saturday, October 12, crews will be completing the paving of the trail surface. On Saturday, October 19, crews will be conducting roadway work.  




Work on the Park Road Trail project will resume beginning the week of October 7th. Paving of the road will begin on October 14th. The project was delayed due to contractor scheduling, but the Township has been working diligently with the contractors and Township engineers to prepare a work schedule for on-time completion of the project. The work is planned to progress as follows:

October 7-11 – Final grading and paving of trail surface.

October 14-18 – Full depth reclamation and paving of the roadway. The full depth reclamation process is time consuming. In order to complete the process efficiently, extended work hours of 7 am to 9 pm have been permitted. One lane of traffic will be open and maintained at all times using flaggers. Emergency services and the Downingtown Area School District have been notified. Please allow additional time for travel in the area and use caution at all times in the construction zone.

October 21-30 – Final paving, signage and crosswalk installation, landscape work, and cleanup.

The Township would like to thank the residents of the Park Road area for their patience in this process.

Facebook Twitter Email